The Construction Phase Plan must set out the arrangements for securing health & safety taking account, where necessary, of industrial, commercial, domestic or transport related activities taking place on the construction site. The following information should be included: A suitable CPP must contain the following areas:
a) A description of the project including key dates and important project team members
b) The management of the work including the, health and safety aims, site rules, arrangements to make sure all team members cooperate and coordinate their work, for example, regular team meetings, arrangements for involving site workers, site induction, welfare facilities, fire and emergency procedures
c) The control of any of the specific site works from Schedule 3 of CDM 2015 if they are relevant to the work
Suitable and sufficient risk assessments and method statements relevant and specific to the tasks, statutory inspections and site safety tours, daily toolbox talks etc